On February 21, 2013, the City of Llano mailed an
“In the Know” newsletter,
written by Lynda Kuder, which distorts the history of our sewer plant and
our “plans” for necessary upgrades.
This paper will attempt to provide a more accurate
picture of our sewer plant’s past and future. Only available documents and
numbers available from 2007 and from the newsletter are used and presented
here.
The hypothesis of this paper is that if Hejl, Lee and
Associates’ and Lynda Kuder’s business case had been complete, then the City
would not be facing millions of dollars of upgrades now. We are still on a
path to make more bad decisions unless we change players and process.
The best available City documents lead to the following
conclusion: the actual total cost for the 2007 plan of renovating the old
sewer plant is $16.5 million. The
total cost of switching to state-of-the-art GE technology would have been
$2.6 million. This is in stark
contrast to the business case presented by the City at the time.